Horace Gray Dushane v. Benedict — Opinion of the Court

It is always desirable to prevent a cross-action where full and complete justice can be done to the parties in a single suit, and it is upon this ground that the courts have of late been disposed to extend to the greatest length compatible with the legal rights of the parties, the principle allowing evidence in defense or in reduction of damages to be introduced, rather than to compel the defendant to resort to his cross-action.' Harrington v.
Source: Wikisource

Horace Gray Dushane v. Benedict — Opinion of the Court

The law does not require a party to pay for imperfect and defective work the price stipulated for a perfect structure, and, when the price is demanded, will allow him to deduct the difference between that price and the value of the inferior work, and also the amount of any direct damages flowing from existing defects, not exceeding the demand of the plaintiffs. This is a rule of strict justice, and the deduction is allowed in a suit upon the contract, to prevent circuity of action.' 21 Wall.
Source: Wikisource

Horace Gray Dushane v. Benedict — Opinion of the Court

Such defenses have always been admitted in our courts. Having no court of chancery, we could not get along without them. To permit the plaintiff to recover the whole purchase money, and leave the defendants to their remedy by an action for fraudulent concealment, would be most unjust. The purchase money and damages arise out of the same transaction, and the proper time for inquiry was before the money was taken from the pocket of the defendants. It might be too late afterwards. And certainly the plaintiff has no right to complain if the whole business is settled at once.
Source: Wikisource

Get perspective with Kwize: daily news enlightened by great literature