Summary

Louis Brandeis Wood v. United States (258 U.S. 120…

There the contract gave to the United States in terms 'the right of suspending the whole or any part of the work.' The absence of such a provision in the contract here under consideration is mainly relied upon to distinguish this case. But here, as there, the contract provided that no claim shall be made or allowed for any damages which may arise out of any delay caused by the United States. Suspension by the government is one of several possible causes of delay-and not an uncommon one.
Source: Wikisource

Get perspective with Kwize: daily news enlightened by great literature