“ The suit was founded on the petition of Adams, claiming a balance against the government on contracts with General Fremont, commanding the Western Military District, for the construction of a certain number of mortar-boats and steam tug-boats, to be used on the Western rivers in the late civil war. The contracts were alleged to have been made on or about the 24th of August, 1861, for the mortarboats, at a cost of $8250 each; and on or about the 10th of September following, for the steam tug-boats, at the cost of $2500 each. ”