“ If, therefore, the contractor takes advantage of his position and of the peculiar form of the specific job contract, as modified by the custom of the trade, to secure deliveries from each of several manufacturers of the full amount of cement required for the particular job, he in effect secures the future delivery of cement not required for the particular job, which he is not entitled to receive, which the manufacturer is under no legal or moral obligation to deliver, and which presumably he would not deliver if he had information that it was not to be used in accordance with his contract. ”