The counsel for the appellee maintains that the Court of Claims in holding as it did for nought the findings and recommendations of the board was right, because the agreement was, that in case of deficiency, the board should 'investigate the facts and report the apparent cause, and assess the amount of loss or injury, and state whether it was attributable to neglect or want of care on the part of the contractor, or to causes beyond his control,' and that their proceedings failed to carry out the intent and terms of the contract in these particulars.
Source: Wikisource

Portrait of Noah Haynes Swayne Noah Haynes Swayne United States v. Shrewsbury — Opinion of the Court

It is a general rule that unless the arbitrator makes his award of all matters submitted to him the award is entirely void.
2. It is next said that if there were any informalities in the reports of the boards of survey, the claimant waived them by acquiescence in the conclusions of the reports and acceptance of payment on the vouchers or bills of lading.
The argument proceeds upon the misapprehension that the contractor obtained an award in his favor, and received the money. Such is not the fact. The board of survey had no jurisdiction over the matter of freight-money