Summary

Portrait of Harold Hitz Burton Harold Hitz Burton First Iowa Hydro-Electric Cooperative v…

The securing of an Iowa state permit is not in any sense a condition precedent or an administrative procedure that must be exhausted before securing a federal license. It is a procedure required by the State of Iowa in dealing with its local streams and also with the waters of the United States within that State in the absence of an assumption of jurisdiction by the United States over the navigability of its waters.
Source: Wikisource

Portrait of Harold Hitz Burton Harold Hitz Burton First Iowa Hydro-Electric Cooperative v…

Water will be pumped from the Mississippi up to the head bays of the power intake dam at the plant to meet possible shortages in supply. The tailrace will extend for a mile along the shore of the Mississippi to a point below Dam 16 on that River. Transmission lines will connect the project with a source of steam standby electric current at Davenport, Iowa, 24 miles up the Mississippi. The plant is expected to produce 200,000,000 kwh. of marketable power per year, of which 151,000,000 kwh. will be firm energy in an average year.
Source: Wikisource

Portrait of Harold Hitz Burton Harold Hitz Burton First Iowa Hydro-Electric Cooperative v…

Section 9 (c) permits the Commission to secure from the applicant 'Such additional information as the commission may require.' This enables it to secure, in so far as it deems it material, such parts or all of the information that the respective states may have prescribed in state statutes as a basis for state action. The entire administrative procedure required as to the present application for a license is described in § 9 and in the Rules of Practice and Regulations of the Commission.
Source: Wikisource